Construction of the new entrance to the inner harbor of the port of Valencia (Valencia, Spain) (Copa America 2007)
Contracting entity: Consorcio Valencia 2007
Year of completion: Ongoing
Lead time: 12 months
Features:
- Dredging: 770,828.42 m3, 16 drawers of 39 203 m long, 19.60 m wide, 16.50 m depth.
- Concrete: HA-30 93941.16 m3. Blloques 18,722.71 m3.
- Steel: B-500-S 3,405,545.93 kg.
- Breakwater:
- 50-250 kg. T 223,416.16;
- 250-500 kg. 176 674 t;
- 500-1000 kg. 15039.79 t;
- T 1-2 t 147,052.58;
- 3-4 t 43,576.49 t
Phase IA Muelle Prat Barcelona (Barcelona, Spain)
Contracting entity: Muelle Prat UTE
Year of completion: In execution
Lead time: 13 months
Features:
- Dredging: 4,083,853 m3
- 25 drawers of 41.301 m long, 18.50 m wide and 17.50 m strut
- Breakwater:
- 50-100 kg: 78,712 t
- 150-400 kg: 16,043 t
- 400-600 kg: p 70760
- 1-2 t: 79 996 t
- 3-4 t: 13 157 t
- 4-3 t: 49 101 t
- > 6 t: 91 673 t
- Todouno: 1,564,101 t
- Screed: 5145 m2
- Filling: 237,438 m3
Construction of screed site customs dock in the inner harbor of the port of Valencia (Valencia, Spain) for the pre-race America's Cup 2004
Contracting entity: Consorcio Valencia 2007
Year of completion: 2004
Lead time: 3 months
Features: The work carried out has been the expansion of the Customs dock, advancing the cliff a length of 35 m, the foundation consists of piles steel columns 30 meters, with concrete ferrailados.